Since the establishment of the company, EKSPRO-2000 realised over 600 designs as a prime contractor or subcontractor for part “Building Structures”. These designs have different scale and complexity.

EKSPRO-2000 prime business focus is the design of building structures of industrial and energy projects in (i.e. nuclear power plants, thermal power plants, gas power plants, water power plants, refineries, pulp and paper factories, chemical plants, metallurgical plants, pharmaceutical plants etc.).

In addition to the industrial designs, the company produces numerous designs of residential buildings, such as family and residential houses, administrative and office buildings, warehouses etc.



 























  • TPP “Maritza East 2” – Steel vertical cylindrical tank with a volume of 90 m3 for storage of technical sulfuric acid with concentration 96% in Demin Water Plant
Site: TPP “Maritza East 2” BG

Sub-site: Steel vertical cylindrical tank with a volume of 90 m3 for storage of technical sulfuric acid with concentration 96% in Demin Water Plant.

Main characteristics of the site:

Material: steel structure
Height: 6 metres
Diameter: 4.50 metres

The project scope includes three tanks for technical sulfuric acid with concentration 96%, which are implemented in various stages. The tanks are situated in Demin Water Plant-external, west of the building. One of them is built on a new foundation, and the other two–on existing foundations for similar tanks which have already been uninstalled.

Project Owner: TPP Maritza East 2 PLC

Designed: year 2015
In operation since: year 2015

Scope of Work: Detailed design of steel vertical cylindrical tank with a volume of 90 m3 for storage of technical sulfuric acid with concentration 96% in Demin Water Plant.