  • "AES 3C Maritza East 1 Power Plant”, Boiler house, Bunker house - cladding and roofing

Site: "AES 3C Maritza East 1 Power Plant”

Sub-site: Boiler house, Bunker house - cladding and roofing

Main characteristics of the site:

Material: steel structure
Height: 95 metres

Customer: AES Corporation
Main contractor: ALSTOM Power Boiler GmbH and
ALSTOM Power Generation AG
Project Owner: ALSTOM Power Boiler GmbH

Designed: year 2010
In operation since: year 2011

Scope of Work: Detailed design of cladding and roofing of Boiler House and Bunker House.